The Bathroom Report: Day 40

Seeing it fully tiled for the first time, I can honestly say that while the shower is still abnormally large, it no longer feels absurdly so. I think when, eventually, the glass gets installed, it will feel like a properly enclosed space. Given the lead time quoted by the glass company, though, it could be a while before I get to make a final determination on that. I was skeptical about both the design and the tile choices originally, but seeing them all hanging together versus laid out on just a sample palette, I’m well pleased with where it’s heading.

The crew here started in on the floor yesterday. Once they get to the point of laying that tile, it should be a straight forwarded running bond pattern covering a simple rectangle. With no oddball angles to contend with, I’m cautiously optimistic that it’ll go quickly. Of course, before they could start on the tile, the heating element needed to be fitted…. and that, of course, is where we encountered this week’s catch.

The heating cable that arrived weeks ago when the materials were delivered turned out to be about half the length they actually needed for the job. Most of what they did yesterday has to come out so that can be corrected. With that, instead of getting the floor most of the way done, they’ve shifted gears to work on grouting the shower tile while waiting for the right cable to show up. That’s fine. It’s still necessary progress. God knows there’s enough grout work that needs doing.

I’m not sure if you’d call it a design feature, but one small thing I insisted on is leaving a 24”x24” corner section of the floor unheated. Since moving in to this house, the master bathroom was almost exclusively a place to keep the litter box. I haven’t decided yet if I’ll move the box back into the bathroom or leave it where it’s been during construction, but in the event it does someday move back into its old space, having a bit of the floor that wouldn’t act like a hot plate under it felt like just good sense. No matter how good a room looks, heated cat pee feels like something best avoided.

I’m not yet willing to call the beginning of the end, but it seems to me that we’re well past the end of the beginning. Once the floor is in and the grout is done, I have to believe we’re in the home stretch. Then it’s moving in the vanity, painting, making the final plumbing connections, and fixtures and finishing touches. It’s still a lot… but a lot less than it was a while ago. 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s