The Bathroom Report: Day 33

It’s the end of another week here at the endless bathroom project. OK, that’s maybe an exaggeration, but it sure feels that way. I assume it’s because we’re now counting days past the originally scheduled finish date and the end still isn’t in sight. 

The end may not be in sight, but there has been some solid progress made this week. The DITRA membrane is on the floor and the shower is (partially) tiled. The tile work has been slow going. I’m told that fitting the pebble floor and some of the angled bits of the first course of wall tile needed to accommodate the long slope of the shower pan took a bit of doing, but it’s in and the first coat of darkener is on it. The crew is plugging away at it, though, so it’s daily visible progress if nothing else. Plus, given the vague memory of my one long ago experience in installing a tile kitchen backsplash, that was considerably less involved than what they’re working on, I’m perfectly happy to let them contend with it.

I’ve mostly given up on projecting when I think this will be finished. I know getting the tile done is the longest pole of this particular tent. The rest – dropping in the vanity and the plumbing and lighting fixtures – should go (theoretically) quickly. That’s what I’ll keep telling myself. It should help to stave off the madness.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s