The Bathroom Report: Day 54

It’s been a busy week even by comparison to the last few busy weeks. 

Because a lot of the ceiling had to come down to accommodate new infrastructure, a metric shit ton of insulation had come down too. The week started with blowing new insulation back into the attic. After that, the designer stopped by to pick paint and look at my unexpectedly mismatched vanity top. The consensus there was to stand pat until the paint is on the walls and fixtures are in before making a final decision. I think we’re all being overly optimistic by hoping that the paint will pull everything together, but I’ve never had a particular eye for color so I’m satisfied to just let the process work through to its logical conclusion.

If it turns out we do need to bring in a substitution, it won’t be the end of the world. Remove two fixtures, replace the existing top with a darker stone, reattach the fixtures, and get on with life. Easy to say, of course, before I have to cut another check for it. In the worst case, I’ll keep the current top stashed in the basement until the time comes to renovate the guest bathroom. That’ll have to be done eventually anyway since it seems some people are fussy about having at least one bathtub in in house. The current number of tubs here is zero and it suits me fine. Maybe it’ll be odd to have dual sinks in a guest bath, but bugger it. I’ve already paid for the damned thing.

The painter has been here for the last two days throwing his own proprietary variant of Lowes’ “Realest Greige” onto the bathroom walls giving the closet a nice coat of contractor standard white. One wall in the bedroom needed repainted due to several spots that had to be cut and patched. Doing one out of four walls wasn’t ideal, but the bedroom is probably the next room on my project list. It needs new carpet and could stand a full paintjob – both of which I was putting off until after the dust and dirt of ripping out and replacing the adjoining bathroom was behind me. 

Final hook ups for plumbing and electrical are scheduled for Monday. I’ll be glad to have the giant box o’ toilet finally out of the laundry room. It’s been there for over two months now. 

Even after all this, there are some punch list items left to do. The mirrors need to be hung. The towel bar and toilet paper holder need to be mounted. A final bead of caulk needs to be run around the top of the shower tile now that the ceiling is painted. With the paint done I can reinstall the blinds and recycle a valance to hide those mechanicals at least temporarily. I’ve also got a small set of shelves I’ll be pressing into service as storage until I stumble across a more permeant storage piece. The shower glass, of course, remains on backorder. But other than that, this project is done.

So, you see, “done” is a matter of degree. 

I suspect I’ll jump the gun and start moving back into the bedroom over the weekend. The temptation to sleep in my own bed after two months across the hall is just too strong to be foiled by whatever additional dirt and grime the electricians and plumbers might kick up next week. How that goes will depend entirely on giving everything a good cleaning. Even with everything swaddled in plastic, tarps, and drop cloths, construction dust seems to be inescapable. Once I get it to a serviceable level of clean, I’m inclined to go ahead and hire someone to really give the whole place a going over from top to bottom. I’ve done a reasonable job to keep the mess from spreading to the rest of the house, but really getting things back up to standard is going to take a level of effort.

That’s it. That’s the update. The end is tantalizingly close and still feels incredibly far away. 

What Annoys Jeff this Week?

1. Estimates. Over the course of the last two days, I’ve tried to come to terms with how bad we are at estimating in complex situations. Starting Tuesday night, the “estimated” time to have power back on 9PM, then 11PM, then unknown, then 3 PM Wednesday, then unknown again, then 11:30 PM, and then finally 11:30 PM Thursday. Grid power came back around midnight on Thursday, so I have no idea where that final estimate came from. This all transpired over the course of 30 hours. I mean wouldn’t it be better to just say we don’t have any fucking idea when things will happen than engage in wildly over optimistic dart throwing? 

2. Connectivity. It’s not the fact that the power is out that’s the problem. In a pinch, I can always make my own. The larger issue is that when the power does happen to go out, I lose nearly all connectivity. Despite Verizon showing that I have two solid bars of LTE coverage, the best I can manage are text messages and some highly garbled phone calls. It’s a $1000 smart phone reduced to less capability than I had from my old Nokia 3310. It’s almost like those “service bars” are a marketing gimmick and have no actual relationship to your actual signal strength. 

3. Social media. You don’t realize how much time you waste on social media until you can’t waste time on social media. Unfortunately, that largely seems to happen when you have nothing but time in front of you. Fortunately, I have a finely honed ability to entertain myself indefinitely, but in a warped and twisted way I did miss being able to have news and world events beamed directly into my eye holes 24/7 via Twitter. 

Bland, uninspired, and quickly forgotten…

For my money, there’s no bigger official waste of working time than the dozen or so yearly online training courses that we’re required to take. Now, don’t misunderstand me, I’m actually a big fan of online education. It’s what allowed me to get a master’s degree while I was traveling around the country for work. When properly designed and executed, online learning can be and is an effective strategy to reach people who otherwise would find that educational opportunity unavailable. 

That being said, the way it’s implemented matters. The “classes” I tool this week were exactly the classes I’ve taken every year for the better part of the last decade. I don’t mean that as an exaggeration. Clicking through the exact same information every year isn’t “continuing education.” It’s not education of any kind. 

I can only assume that the people who control these online classes expect that the average person is too stupid to retain information for more than 365 days. That’s probably true for some segment of the population. If you want them to remember something you have to beat them over the head with it at every opportunity. Even so, it’s farcical to call a program like that “training.”

All I’m saying is that if the intent is just to check a box and say you’ve provided training on whatever topic to your employees, but don’t want to take the time and effort to make it meaningful in any way, how about not making it 95 separate screens to click though before I can print the certificate. If the instructional designers and leaders who approve that mess aren’t going to even pretend that content and engagement are important, you’d better believe that my only goal is to click though as quickly as possible so I can get on with my day.

I’m all for education. I’m a big advocate for getting more knowledge. I am, however, also violently opposed to time-sucking, procedural nonsense that has no purpose other than satisfying some obscure regulation. If that’s what passes for education, no one should pretend to be shocked when anything that follows is equally bland, uninspired, and quickly forgotten.

Return from a wasted week off…

After a week off that was decidedly not a vacation, I’m back to work. Admittedly, it’s working from home, so it’s not nearly as onerous as it could be, but I wasn’t in any way ready to come back to the world of answering emails, fighting online systems, and generally being a productive and responsible adult.

Look, there’s nothing inherently bad about my particular job. I’m not out there laying asphalt in 100-degree heat or slinging hay bales into the loft. I’ve got a decent chair, a good desk, and a couple of monitors that bombard me with information for eight hours every day. It’s hardly rocket science. It’s not usually particularly hard work, even if it does demand pretty close attention to detail and some higher order processing skills from time to time. 

I’ve been doing some variation of it since January 2003. By this point, there’s not much new under the sun. Sure, some of the details change. When I started, Iraq was the talk of the town. Now it’s Ukraine. Different players, same game. The broad strokes have changed very little. Do any job long enough and I suppose you’ll find a rhythm in it. 

So, I’m back at the keyboard. I’ll do the work and I’ll do it well, but I won’t pretend to be thrilled or excited or meeting a great new challenge every day. I do my part to keep the gears of the bureaucracy grinding along because I seem to have a, perhaps unfortunate, talent for it. I’m trading my time for their money and will keep after it until I hit my own magic number and don’t have to do it anymore. 

I’m most definitely a creature of habit, but this is one I’ll be happy to break out of at the first financially responsible opportunity. 

The Bathroom Report: Day 47

It’s been a busy week. Some of that urgency is probably driven by the fact that the guy leading the crew here is due to leave for vacation this time next week. Part of it, I’m sure, is that with the tile done, the pace with which things fall into place naturally increases. Maybe it’s not a sprint to the finish, but it’s better than the last few weeks which have felt like limping towards an ending with one leg mangled in a bear trap.

The progress summary for this week includes all tile being in and grouted, the vanity, top, and sinks are in place, mirrors have been dropped off for framing, and there’s been some minor prep done for painting. The long poles that remain look like setting the toilet, adding in fixtures, paint, putting shelving back in the closet, and setting the shower glass. That last bit will surely drive this project well past day 60 even if all the rest does happen to be finished by the end of next week… though I obviously have my doubts about hitting that mark.

No week is complete without a snag, of course. This week’s issue is the vanity. The finish that leaned towards brown in samples has a decidedly reddish hue in person. I selected it and the top originally because it looked like they would pick up the brown tones in the shower tile. As it turns out, the tile sample we looked at may have had loads of brown in sample size, but it leans decidedly gray in bulk, so I’ve got this very nice vanity that doesn’t really blend with anything. I’m at a complete loss to figure out how the samples looked so good together only to end up this off base. And yes, I even double-checked invoices and labels against the samples to make sure it was even the right product. 

As it sits, it looks like the vanity and top were picked in seclusion from the shower and floor tiles. It’s an unsettling look. So now I’m launching deep discussions with the designer and probably the painting subcontractor on what’s the best way to fix it. Some of it can probably be mitigated by whatever paint eventually ends up on the walls. There’s also the option of re-staining or painting the cabinets to bring them more in line. The nuclear option, and one that’s still very much on the table, is just living with it until something in a new and more harmonious finish can be ordered, built, and shipped in. I know what direction I’m leaning, but it’s probably not a decision I’ll want to finalize until the rest of the bits and pieces are laid in. It seems like every time a new element gets introduced all the others look vaguely different. I’d like to avoid, if possible, creating a do loop of calling for new cabinetry, tops, and paint that carries on infinitely into the future. I’d also prefer not to spend any additional big tranches of cash until I know with more precision what exactly needs changed to make it all hang together. 

As we close the week, the wheels feel like they’ve come a bit off. It’s not an ideal note on which to end the week, but it’s exactly why I built in a 15% slush fund into the budget. Spending the money honestly doesn’t feel like the worst of it. That dubious distinction belongs to the knowledge that getting it sorted will add more time to a project I desperately hoped was drawing towards an end.

What Annoys Jeff this Week?

1. Blame and credit. OK, it’s fashionable to blame Joe Biden for interest rates and inflation and gas prices and whatever else anyone believes is going off the rails at any given time. Fine. Taking the blame is an occupational hazard of being president. I think, though, we’re missing some of the up side of the current economic environment – namely that gas prices and generationally high inflation levels have apparently made backyard fireworks a budget line item that was ripe to dramatically decrease or be cut out completely for people in 2022. With only a few individual outliers, personal fireworks displays within earshot of the homestead were constrained almost exclusively to between 9:00 PM and 10:00 PM on Independence Day and were dramatically smaller and less intrusive to the general peace and tranquility of the evening than they have been in previous years… so, thanks, Biden. I mean if we’re going to blame him for global economic forces at work, he might as well get some credit for the good stuff he doesn’t have any control over.

2. Time. The standard work week lasts approximately 375 hours. A week of vacation time wraps up in just short of one hour and 26 minutes. I know here are psychological reasons why we perceive the passage of time differently under various conditions, but that doesn’t make the fact any less annoying – particularly when your most recent batch of days off is quickly diminishing. It this case, perception is stupid and I hate it.

3. Religion. I’ve covered it before, but it bears repeating: I’m under no moral, ethical, or legal obligation to follow the tenants of your religion. I don’t care if you follow the old gods, the new gods, the Greek pantheon, Sol Invictus, Vishnu, Buddha, or Jesus Christ himself. Your beliefs govern the way you live your life. The minute you turn your faith into a belaying pin to cudgel others about the head and neck, no matter what peace and love you preach, I’ll oppose you loudly, at length, and with whatever force is necessary to get you to cease pummeling others with your interpretation of faith and goodness. You’d think in the year of our lord two thousand and twenty-two we might have left some of this medieval fuckery in the rear view, and yet here we are. 

A dream of osmosis…

After nearly two full months, I can honestly say I haven’t loved my time in the guest room. I’m sure the bed is perfectly serviceable for a weekend visit or maybe even for a week or two. Because we all light up the front of our houses like good suburbanites, there’s also way too much ambient light bleeding in the front windows. I tend to prefer near total darkness for sleep. I’m sure that’s something I could correct with updated curtains, but I’m determined to ride this out as a temporary expedient that doesn’t require the addition of blackout shades.

I won’t pretend this temporary relocation has been all bad, though. What I have enjoyed is sleeping in part of the library. The guest bedroom, you see, does double duty as the holding area for my to-be-read nonfiction pile. It’s a few hundred books I want to read coving just about all the high points – and many of the low ones – of western civilization. There are absolute shit tons of wisdom stacked in those volumes. I know it won’t transfer by osmosis, but having it that close at hand through the night is somehow comforting.

I suppose this means there will be bookshelves making their way to the master bedroom sooner or later. It won’t happen immediately, because I don’t even want to think of laying in bookcases until I can arrange to have the carpet replaced. Believe me when I say that’s the kind of thing you want to consider in advance before picking a new spot to accumulate a few hundred pounds of paper and glue and binding. You don’t really want to spend your time moving stacks and stacks of books more than once if there’s any reasonable way to avoid it.

So, that’s now another couple of projects tagged on to a list of things to do that never seems to get shorted. Must be one of those joys of home ownership I keep hearing about.

Men plan and the gods laugh…

My annual birthday week book buying spree was interrupted, as you know, by the long-awaited master bathroom remodeling project. At the time, I pinned my hopes to get back to the world of dusty, mote filled shops during the next block of leave I usually take during the first week of July. Then, of course, there was the repeated county inspection fiasco that set us back by a matter of weeks. 

That sad story brings us to where we are now – the first week of July – when I once again have vast sweeps of unallocated time that I planned to use for chasing books. Here, I am, though, tethered to the house while work in the bathroom continues.

This summer won’t go down in my personal history as the best use of vacation time I’ve ever experienced. Given how many small change decisions it’s helpful to be able to discuss and make on the spot, the only real alternative was to cancel out my leave this week and log in for another session of working from home. That thought was even less enticing than just pissing away 4 days of leave doing piddling odds and ends around the house. 

After last week’s water system blowout, I’d be wildly uncomfortable being away for any real length of time. I’ve snuck away for a few appointments during this process – those that have taken months to get and that changing ranked as too hard to do – but otherwise I’ve been able to be here throughout. As this effort drags on, though, I increasingly wonder about the sanity of anyone who stays in their home through a more involved renovation that isn’t just contained to one room.

I’m sure at some point this week, I’ll scour a few of the online shops I frequent, just to scratch the acquisition itch. Otherwise, it looks like a week of reprising those distant times of puppy training when all the creatures of the household piled into the kitchen. I suppose, spending a few days huddled up with books, tea, and furry critters isn’t really the worst bit of vacation time I’ve ever spent… but it wasn’t at all what I had planned.

The Bathroom Report: Day 40

Seeing it fully tiled for the first time, I can honestly say that while the shower is still abnormally large, it no longer feels absurdly so. I think when, eventually, the glass gets installed, it will feel like a properly enclosed space. Given the lead time quoted by the glass company, though, it could be a while before I get to make a final determination on that. I was skeptical about both the design and the tile choices originally, but seeing them all hanging together versus laid out on just a sample palette, I’m well pleased with where it’s heading.

The crew here started in on the floor yesterday. Once they get to the point of laying that tile, it should be a straight forwarded running bond pattern covering a simple rectangle. With no oddball angles to contend with, I’m cautiously optimistic that it’ll go quickly. Of course, before they could start on the tile, the heating element needed to be fitted…. and that, of course, is where we encountered this week’s catch.

The heating cable that arrived weeks ago when the materials were delivered turned out to be about half the length they actually needed for the job. Most of what they did yesterday has to come out so that can be corrected. With that, instead of getting the floor most of the way done, they’ve shifted gears to work on grouting the shower tile while waiting for the right cable to show up. That’s fine. It’s still necessary progress. God knows there’s enough grout work that needs doing.

I’m not sure if you’d call it a design feature, but one small thing I insisted on is leaving a 24”x24” corner section of the floor unheated. Since moving in to this house, the master bathroom was almost exclusively a place to keep the litter box. I haven’t decided yet if I’ll move the box back into the bathroom or leave it where it’s been during construction, but in the event it does someday move back into its old space, having a bit of the floor that wouldn’t act like a hot plate under it felt like just good sense. No matter how good a room looks, heated cat pee feels like something best avoided.

I’m not yet willing to call the beginning of the end, but it seems to me that we’re well past the end of the beginning. Once the floor is in and the grout is done, I have to believe we’re in the home stretch. Then it’s moving in the vanity, painting, making the final plumbing connections, and fixtures and finishing touches. It’s still a lot… but a lot less than it was a while ago.